Successful Relocation of High-Precision Product Assembly and Sheet Metal Production

When a partner’s production facility was sold, VIDEOTON managed a complex, time-critical production relocation, covering sheet-metal manufacturing, sub-assemblies, and final assembly of a letter folding machine. Despite the challenges, VIDEOTON's team ensured a stable transition.

  • Driver: Business restructuring relocation
  • Member company: VT ES Kft., Hungary
  • Country of origin: Netherlands
  • Production Area: 2000 sqm production / 1000 sqm warehouse
  • Direct headcount: 75 assembly + 25 sheet-metal
  • Suppliers / PNs taken over: 147 / 2100
  • Product Variants: 106
  • Transfer time: 1-1,5 years

Background of the transfer project

The partner sold their production facility, making relocation unavoidable. This required the full transfer of sheet-metal manufacturing, sub-assemblies, and final assembly to a new location. A major additional challenge was incomplete, outdated, or missing technical documentation, which increased operational and quality risks during the transfer.

VIDEOTON's solution

Our assembly team completed several weeks of intensive, hands-on training to fully understand product structure and assembly details. In parallel, the technology department reviewed, corrected, and re-created all missing manufacturing and assembly documentation to ensure stable serial production.